The three-week look-ahead, and a free template that runs it
Every trade meeting in commercial construction runs on the same document: the three-week look-ahead. It’s the slice of the schedule short enough to be real and long enough to coordinate — and for a concrete sub it’s where pours, crews, and everyone else’s trades collide. This is a free Excel version built to be actually maintained, which is the entire battle.
Download the Look-Ahead Template (.xlsx) →
Works in Excel and Google Sheets. Free for use within your company.
What’s inside
- Type one date, get the whole grid — enter the Monday the look-ahead starts and all eighteen day headers and three week bands fill themselves. The Monday roll is one cell, not a morning of retyping.
- One row per activity — job, the activity in field language, whose crew it is, and a crew count in each working day.
- A men-per-day total — the bottom row sums every column, so the week that quietly plans 34 men against your 22 announces itself.
- Example rows and a legend — blue cells are yours; overwrite the examples.
- Print-ready — landscape Letter, one page wide, made for the coordination meeting table.
How to run the weekly roll
- Same day every week — Monday morning, before the coordination meeting, retype the start date and plan the new week three. The roll is the discipline; a look-ahead that skips a week is a look-behind.
- Foremen feed it, one person owns it — crew counts come from the people running the work, but a single owner keeps it honest.
- Week one firm, week three provisional — and say so out loud. Pretending week three is firm teaches the GC to ignore your week one.
- Check the bottom row against your actual headcount — that one glance is the cheapest gap analysis there is.
Where the spreadsheet stops
Three honest limits. The roll erases history — last week’s plan is gone the moment you retype the date. Nothing checks the crew math — two rows can claim the same crew and the sheet adds them up happily. And when a pour in week one moves, the sheet tells no one. That’s the shape of the upgrade when it comes: on the pour board, the 90-day rolling Lookahead rolls itself, planned pours graduate through an approval step instead of a retype, the crew math is checked against the real roster — and a change notifies the people rolling toward it.
Run the next three weeks on it
Take the template and run Monday’s meeting on it — it’s free either way. And when the roll, the history, and the crew math start costing you, put one week on a Lookahead that rolls itself. Planning Ops is built for concrete subs, veteran-owned, with a 14-day free trial and your whole crew riding free as viewers. See the Rolling Lookahead →