The three-week look-ahead, and the free templates that run it
Every trade meeting in commercial construction runs on the same document: the three-week look-ahead. It’s the slice of the schedule short enough to be real and long enough to coordinate — and for a concrete sub it’s where pours, crews, and everyone else’s trades collide. This is a free Excel version built to be actually maintained, which is the entire battle. It comes in four horizons — the standard three weeks, plus two-week, weekly and six-week versions — same grid, same one-cell roll.
Download the 3-Week Look-Ahead Template (.xlsx) →
Works in Excel and Google Sheets. Free for use within your company.
What’s inside
- Type one date, get the whole grid — enter the Monday the look-ahead starts and all eighteen day headers and three week bands fill themselves. The Monday roll is one cell, not a morning of retyping.
- One row per activity — job, the activity in field language, whose crew it is, and a crew count in each working day.
- A men-per-day total — the bottom row sums every column, so the week that quietly plans 34 men against your 22 announces itself.
- Example rows and a legend — blue cells are yours; overwrite the examples.
- Print-ready — landscape Letter, one page wide, made for the coordination meeting table.
Pick the horizon
Same grid, same blue cells, same one-cell roll — the only thing that changes is how far out you are looking and what a column means.
| Horizon | What it is for | Columns | Download |
|---|---|---|---|
| Weekly | The foremen’s week: activities, crew per day, and the note that makes each day happen. Firm by Friday for the week after. | 6 days + notes | Weekly template (.xlsx) |
| Two-week | Fast-turning jobs, and GCs that run a two-week coordination meeting. | 12 days | Two-week template (.xlsx) |
| Three-week | The commercial standard: this week firm, next week committed, week three provisional. | 18 days | Three-week template (.xlsx) |
| Six-week | Make-ready: crew per week, and the constraint that gates each activity, with an owner and a date. | 6 weeks + constraints | Six-week template (.xlsx) |
The two-week look-ahead
Twelve day columns instead of eighteen. Run it when the GC’s meeting is a two-week meeting, or when the job turns fast enough that week three was never more than a guess. The roll is the same — retype the Monday, week two becomes week one, plan the new week two. If week two keeps surprising you, that’s the signal to move up to three.
The weekly look-ahead
One week, six days, and a notes column. This is the sheet you hand out, not the one you plan on: the foremen’s week, firm by Friday for the week after, with the thing that makes each day real written next to it — pump booked for 6 AM, inspection passed Tuesday, rebar on site Wednesday morning. Plan the weeks beyond it on the two- or three-week version; print this one.
The six-week look-ahead: make-ready, not crew-by-day
Past three weeks, planning crew by the day is theater. What six weeks is for is make-ready: the Last Planner habit of naming, for every activity, the constraint that has to clear before it can start — material on site, RFI answered, inspection scheduled, access, the crew itself — and who owns clearing it by when. So the six-week template changes the columns: one per week, with the planned crew per week, plus a constraint column and an owner-and-due column. An activity with an open constraint inside week two is a problem today, not in week two. Roll it weekly like the others; anything that reaches week three with its constraint still open goes onto the three-week sheet as a risk.
How to run the weekly roll
- Same day every week — Monday morning, before the coordination meeting, retype the start date and plan the new week three. The roll is the discipline; a look-ahead that skips a week is a look-behind.
- Foremen feed it, one person owns it — crew counts come from the people running the work, but a single owner keeps it honest.
- Week one firm, week three provisional — and say so out loud. Pretending week three is firm teaches the GC to ignore your week one.
- Check the bottom row against your actual headcount — that one glance is the cheapest gap analysis there is.
Where the spreadsheet stops
Three honest limits. The roll erases history — last week’s plan is gone the moment you retype the date. Nothing checks the crew math — two rows can claim the same crew and the sheet adds them up happily. And when a pour in week one moves, the sheet tells no one. That’s the shape of the upgrade when it comes: on the pour board, the 90-day rolling Lookahead rolls itself, planned pours graduate through an approval step instead of a retype, a double-booked crew is flagged the moment it’s assigned — and a change notifies the people rolling toward it.
Run the next three weeks on it
Take the template and run Monday’s meeting on it — it’s free either way. And when the roll, the history, and the crew math start costing you, put one week on a Lookahead that rolls itself. Planning Ops is built for concrete subs, veteran-owned, with a 14-day free trial and your whole crew riding free as viewers. See the Rolling Lookahead →